The Devil’s Gate Reservoir Annual Cleanout will be under construction this year from July through October. The 120,000 Cubic Yards will be hauled using up to 300 truck trips per day to Sheldon Pit.
The hauling trucks would travel west on the 210 Freeway, west on Foothill Blvd to Osborne Street, south on Osborne Street, east on Glenoaks Blvd, north on Sheldon Street, and then left into Sheldon Pit. Then on the return, the trucks would go south on Sheldon Street, west on Glenoaks Blvd, north on Osborne Street, and east on Foothill Blvd to the 210 freeway. Hauling will be conducted Monday through Friday from 7 am to 4:30 pm, excluding any holidays. No trucks should be going on any streets in Shadow Hills.